HOME  |   ABOUT US  |   VACANCIES  |   CONTACT US  
AMS No-Dig Directional Drilling and Auger Boring Specialists
  HOME | DIRECTIONAL DRILLING | GUIDED AUGER BORING | ACCREDITATIONS |  FLEET |  EQUIPMENT SALES |  CASE STUDIES  
 
 
 

CASE STUDY: Lock Ryan WwTW

View all case studies


Project Summary
Scottish Water is currently constructing an 800mm discharge pipeline from the Lock Ryan WwTW in Port Rodie, Stranraer discharging through a diffuser into the Irish Sea.

AMS No Dig Ltd, commissioned by contractor Leslie MWH Joint Venture recently completed the installation of the Sea outfall section by HDD techniques.

Project Details
The sea outfall section involved passing under an existing railway line and sea revetment terminating 3m below the sea bed in a pre-constructed cofferdam.

The design, planning and approval process took two years to complete before construction commenced in February 2015. AMS were involved throughout the process and prepared detailed construction proposals including commissioning of calculations necessary to gain construction approval from Network Rail and the port authority, the organisation responsible for the Revetment.

Construction
AMS mobilised to site late January 2015 with site set up completed within seven working days. Drilling commenced on the 12th February under 24 hour working conditions which was a requirement of the contract. Pipe installation was completed on 20th February within programme.

AMS No-Dig’s Prime Drilling PD60/30 HDD rig met the required specification of the installation works perfectly. The PD 60/30 Drilling Rig is a heavily engineered machine capable of producing 60 tonnes pull force with 30,000 NM of rotary torque.

  Click images to enlarge Cross Section of the Drill profile
Cross Section of the Drill profile

Site setup at Port Rodie including the Prime PD60/30 and mud recycling equipment
Site setup at Port Rodie including the Prime PD60/30 and mud recycling equipment

Pilot drill exiting the coffer dam
Pilot drill exiting the coffer dam

Pipeline positioned on the sea barge during installation
Pipeline positioned on the sea barge during installation

View all case studies

 


 
  AMS No-Dig Ltd, Brigg Road, Scunthorpe, DN16 1AP
AMS No-Dig Ltd is Registered in England No. 02703484 : VAT Registration No.: GB 651 531 457
© 2017 AMS No-Dig Ltd